St. Joseph Regional Medical Center

SCOPE OF PROJECT

Overview
Construct new 20,000 Sq. Ft. Central Energy Plant for the Saint Joseph Regional Medical Center.
Installation of Medium Voltage Main Service and associated electrical distribution.
This projects overall cost is mainly attributed to the switchgear costs. 

Energized Electric Team
Eric Martin
Project Manager

Project Location

St. Joseph Regional Medical Center
415 6th Street
Lewiston Idaho 83501

Final Contract Amount: $5.2M

Project Schedule/Completion

Started – 2015
Completed – 2017

Project Owner
St. Joseph Medical Center
415 6th Street
Lewiston Idaho 83501


General Contractor
Bouten Construction
627 North Napa Street
Spokane, WA 99220 

Architect
Kirchner Architecture
415 North McKinley Drive, Suite 1145
Little Rock, Arkansas 72205 

Electrical Engineer
TME, Inc.
5800 Evergreen Drive
Little Rock, Arkansas 72205