SCOPE OF PROJECT

Overview
Phase demolition, remodel and Construction of the new Shadle Park High School of over 230,000 Sq. Ft.
Complete re-modernization of educational complex, while occupied, involving over 12 phases requiring precise coordination.
Complete renovation of electrical systems, paging, fire alarm systems, data and communication systems.

Energized Electric Team
Eric Martin
Project Manager

Project Location

AC Davis High School
212 S. 6th Avenue
Yakima, WA 98902

Final Contract Amount: $8.7M

Project Schedule/Completion

Started – November 2012
Completed – August 2015

Project Owner
Yakima School District
205 N. 4th Ave
Yakima, WA 98902


Electrical Engineer

Conley Engineering Inc.

205 N. 40th Ave, Suite 201

Yakima, WA 98908

 

General Contractor

Absher Construction
1001 Shaw Road
Puyallup, WA 98372

 

Architect

Loofburrow Wetch Architects
201 W. Yakima Ave.
Yakima, WA 98902